Methovini Ecde

Ongoing GoMC-PMTS-2024-8108
Project Description
Construction of 2no. ECDE Classrooms with an office,3-Door Pit Latrine with Urinal,Electrical Works,Shelving to the stores, 2No.lockable metallic cabinets,2No. Wooden Desks,2No. Wooden Arm Chairs,Water harvesting goods (10,,000Ltrs Water Tank and base),40 No. Kiddy chairs and 20. No. Kiddy tables,Play equipment 4 piece set (double swing, slide, climbing frame and double see-saw),Display soft board and Branding, Publicity and Signwriting
Budget & Expenditure
Approved
KES 4.30M
Contract
KES 4.04M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8108
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start26 Nov 2024
  • End26 Apr 2025
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Floated
Phase Two · 24 Oct 2024
Awarded
Phase Two · 26 Nov 2024
Site Handover
Phase Three · 16 Dec 2024
Not Started
Phase Two · 16 Dec 2024
Ongoing
Phase Three · 14 Feb 2025