Makueni Child Protection Centre-hq

Completed GoMC-PMTS-2024-3346
Project Description

-operationalization, electrification and equipping, Solarization

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3346
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateGender, Children and Social Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 22 Nov 2024
Approved Requisition
Phase Two · 04 Dec 2024
Floated
Phase Two · 04 Feb 2025
Awarded
Phase Two · 14 Mar 2025
Site Handover
Phase Three · 27 Mar 2025
Not Started
Phase Three · 27 Mar 2025
Ongoing
Phase Three · 27 Mar 2025
Completed