Katangini Ecde

Ongoing GoMC-PMTS-2024-1126
Project Description

Construction of one classroom, office and store. Installation of a water tank

Budget & Expenditure
Approved
KES 2.47M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1126
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 21 Jan 2025
Floated
Phase Two · 03 Feb 2025
Awarded
Phase Two · 10 Mar 2025
Site Handover
Phase Three · 19 Mar 2025
Not Started
Phase Three · 19 Mar 2025
Ongoing
Phase Three · 24 Mar 2025