Lungu Borehole

Completed GoMC-PMTS-2024-2025
Project Description

Equipping, solarisation and a water point kiosk

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 2.77M
Spent
KES 2.75M
Utilisation
100%
Budget Utilisation
Gallery (1 photos)
Lungu Borehole
Lungu Borehole
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2025
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start30 Jan 2025
  • End30 May 2025
Timeline
Cabinet Paper Approved
Phase One · 15 Dec 2024
Approved Requisition
Phase Two · 17 Dec 2024
Floated
Phase Two · 14 Jan 2025
Awarded
Phase Two · 24 Jan 2025
Site Handover
Phase Three · 30 Jan 2025
Not Started
Phase Three · 11 Feb 2025
Ongoing
Phase Three · 12 Feb 2025
Completed
Phase Three · 18 Mar 2025