Kituasi Water Project

Completed GoMC-PMTS-2024-3502
Project Description

Construction of 4 inch raising main to Kwa Wambua Kimeu, solarization and electricity, installation of pump set, elevated metallic water tank (100m3).

Budget & Expenditure
Approved
KES 10.00M
Contract
KES 0.00
Spent
KES 10.00M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3502
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 10 Jan 2025
Approved Requisition
Phase Two · 15 Jan 2025
Floated
Phase Two · 13 Feb 2025
Awarded
Phase Two · 24 Apr 2025
Site Handover
Phase Three · 30 Apr 2025
Not Started
Phase Three · 30 Apr 2025
Ongoing
Phase Three · 25 Apr 2025
Completed
Phase Three · 20 Jul 2025