Supply Of Water Tanks And Distribution Pipes For Mandela, Kweleli, Syaolwe, Kwa Moto And Isololo Water Project

Completed GoMC-PMTS-2024-8735
Project Description

Supply of Water tanks and distribution pipes mandela, Kweleli, Syaolwe, Kwa Moto and Isololo water project

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 0.00
Spent
KES 6.23M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8735
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Jan 2025
Approved Requisition
Phase Two · 28 Jan 2025
Floated
Phase Two · 05 Feb 2025
Awarded
Phase Two · 17 Mar 2025
Site Handover
Phase Three · 20 Mar 2025
Not Started
Phase Three · 20 Mar 2025
Ongoing
Phase Three · 20 Mar 2025
Completed
Phase Three · 17 Apr 2025