Drilling And Equipping Of Yekanga Borehole

Completed GoMC-PMTS-2024-8075
Project Description
General items and preliminaries ,solarization, supply and installation of borehole pump and accessories ,fencing of borehole area ,water connection to Yekanga water kiosk and Yekanga secondary school
Budget & Expenditure
Approved
KES 5.00M
Contract
KES 5.00M
Spent
KES 5.00M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8075
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start20 Jun 2025
  • End30 Aug 2025
Timeline
Cabinet Paper Approved
Phase One · 02 Apr 2025
Approved Requisition
Phase Two · 08 Apr 2025
Floated
Phase Two · 27 May 2025
Awarded
Phase Two · 19 Jun 2025
Site Handover
Phase Three · 24 Jun 2025
Not Started
Phase Three · 20 Jun 2025
Ongoing
Phase Three · 20 Jun 2025
Completed
Phase Three · 15 Aug 2025