Kimundi Water Project

Completed GoMC-PMTS-2024-5718
Project Description

 Repair of pipeline, provision of water tanks and solar repairs replacement

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.38M
Spent
KES 1.38M
Utilisation
91.9%
Budget Utilisation
Gallery (4 photos)
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Kimundi Water Project
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5718
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start24 Oct 2024
  • End15 Nov 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 26 Sep 2024
Floated
Phase Two · 04 Oct 2024
Awarded
Phase Two · 22 Oct 2024
Site Handover
Phase Three · 29 Oct 2024
Not Started
Phase Two · 29 Oct 2024
Ongoing
Phase Three · 24 Oct 2024
Completed
Phase Three · 15 Feb 2025