Kitise Water Project

Completed GoMC-PMTS-2024-7538
Project Description

Upgrading of 3" rising main



Budget & Expenditure
Approved
KES 1.00M
Contract
KES 8.50M
Spent
KES 1.00M
Utilisation
100%
Budget Utilisation
Gallery (1 photos)
Rehabilitation Of Kitise Water Project
Rehabilitation Of Kitise Water Project
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7538
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Nov 2024
  • End28 Feb 2025
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2024
Approved Requisition
Phase Two · 29 Oct 2024
Floated
Phase Two · 30 Oct 2024
Awarded
Phase Two · 19 Nov 2024
Site Handover
Phase Three · 26 Nov 2024
Not Started
Phase Two · 26 Nov 2024
Ongoing
Phase Three · 28 Nov 2024
Completed
Phase Three · 28 Feb 2025