Cabinet Paper Approved
Phase One · 05 Sep 2024
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 18 Sep 2024
Approved Requisition
Phase Two · 18 Sep 2024
Approved Requisition
Phase Two · 18 Sep 2024
Floated
Phase Two · 19 Nov 2024
Floated
Phase Two · 19 Nov 2024
Floated
Phase Two · 19 Nov 2024
Awarded
Phase Two · 24 Dec 2024
Site Handover
Phase Three · 20 Jan 2025
Not Started
Phase Three · 20 Jan 2025
Ongoing
Phase Three · 26 Jan 2025
Completed
Phase Three · 30 Jun 2025