Mukameni Borehole Water Project

Completed GoMC-PMTS-2024-4049
Project Description

Rehabilitation and extension of project pipeline-3800m

Construction of 1No R-M water kiosk

Rehabilitation of 1N0 water kiosk

Budget & Expenditure
Approved
KES 6.00M
Contract
KES 902.3K
Spent
KES 902.3K
Utilisation
15%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4049
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start25 Oct 2024
  • End25 Dec 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 26 Sep 2024
Floated
Phase Two · 03 Oct 2024
Awarded
Phase Two · 23 Oct 2024
Site Handover
Phase Three · 30 Oct 2024
Not Started
Phase Two · 30 Oct 2024
Ongoing
Phase Three · 25 Oct 2024
Completed
Phase Three · 20 Dec 2024