Distribution Of Water From Itaa Borehole To Kwa Kiviku

Completed GoMC-PMTS-2024-9861
Project Description
General items and preliminaries , water connection to Kwa Mutunga water kiosk
Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 913.8K
Utilisation
91.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9861
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 17 Feb 2025
Approved Requisition
Phase Two · 18 Feb 2025
Floated
Phase Two · 01 Apr 2025
Awarded
Phase Two · 24 Apr 2025
Site Handover
Phase Three · 30 Apr 2025
Not Started
Phase Three · 30 Apr 2025
Ongoing
Phase Three · 01 May 2025
Completed
Phase Three · 20 Jun 2025