Installation Of Pumping Unit,flashing Of Kwa Mwenga Borehole

Completed GoMC-PMTS-2024-1420
Project Description
Mobilization and demobilization of plant, machinery, equipment and personnel for  satisfactory execution of works, borehole flashing using county rig, replacement of submersible pump, rehabilitation of of water supply networks, supply of 10cm3 plastic tank, construction of borehole chamber
Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 764.5K
Utilisation
76.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1420
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 15 Dec 2024
Approved Requisition
Phase Two · 16 Dec 2024
Floated
Phase Two · 10 Feb 2025
Awarded
Phase Two · 21 Mar 2025
Site Handover
Phase Three · 19 Mar 2025
Not Started
Phase Three · 19 Mar 2025
Ongoing
Phase Three · 20 Mar 2025
Completed
Phase Three · 25 Jun 2025