Rehabilitation Of Kikumini Borehole

Completed GoMC-PMTS-2024-5295
Project Description

Solarization, elevation tank, Rehabilitation of pipeline from source to Kona Baridi, Kari, Central and Kikumini Market.

Budget & Expenditure
Approved
KES 5.50M
Contract
KES 0.00
Spent
KES 5.50M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5295
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Jan 2025
Approved Requisition
Phase Two · 29 Jan 2025
Floated
Phase Two · 06 Feb 2025
Awarded
Phase Two · 24 Mar 2025
Site Handover
Phase Three · 29 Mar 2025
Not Started
Phase Three · 29 Mar 2025
Ongoing
Phase Three · 30 Mar 2025
Completed
Phase Three · 20 Jun 2025