Kyanzisi Water Project Phase 1

Completed GoMC-PMTS-2024-1279
Project Description

Phase 1: Sand dam construction, 50m3 sump construction, pumping system installation, installation of 2km pipeline to Kaembeni tanks, and rehabiliattion of kiosk at Kaembeni

Budget & Expenditure
Approved
KES 7.00M
Contract
KES 0.00
Spent
KES 7.00M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1279
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Feb 2025
Approved Requisition
Phase Two · 28 Jan 2025
Floated
Phase Two · 07 Feb 2025
Awarded
Phase Two · 12 Mar 2025
Site Handover
Phase Three · 20 Mar 2025
Not Started
Phase Three · 20 Mar 2025
Ongoing
Phase Three · 27 Mar 2025
Completed
Phase Three · 09 Jun 2025