Repair And Distribution Of Nzaini Bh

Completed GoMC-PMTS-2024-8330
Project Description

Repair and distribution of Nzaini Borehole - Repair and distribution of Nzaini Borehole

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 2.00M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8330
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 04 Nov 2024
Approved Requisition
Phase Two · 05 Nov 2024
Floated
Phase Two · 18 Nov 2024
Awarded
Phase Two · 19 Dec 2024
Site Handover
Phase Three · 10 Jan 2025
Not Started
Phase Three · 10 Jan 2025
Ongoing
Phase Three · 20 Dec 2024
Completed
Phase Three · 24 Jul 2025