Desilting Of Kwa Loa Earthdam

Completed GoMC-PMTS-2024-1445
Project Description

Desilting of Kwa Loa Earthdam

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 0.00
Spent
KES 3.24M
Utilisation
92.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1445
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 15 Dec 2024
Approved Requisition
Phase Two · 16 Dec 2024
Floated
Phase Two · 20 Jan 2025
Awarded
Phase Two · 12 Feb 2025
Site Handover
Phase Three · 20 Feb 2025
Not Started
Phase Three · 20 Feb 2025
Ongoing
Phase Three · 22 Feb 2025
Completed
Phase Three · 03 Apr 2025