Ithanze Water Project

Completed GoMC-PMTS-2024-3590
Project Description

2.5Km water distribution pipeline while connecting existing Ithanze Water kiosk

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 2.81M
Spent
KES 5.69M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3590
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start04 Dec 2024
  • End15 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 10 Oct 2024
Approved Requisition
Phase Two · 15 Oct 2024
Floated
Phase Two · 21 Nov 2024
Awarded
Phase Two · 19 Dec 2024
Site Handover
Phase Three · 11 Dec 2024
Not Started
Phase Two · 11 Dec 2024
Ongoing
Phase Three · 11 Dec 2024
Completed
Phase Three · 29 May 2025