Itenge Water Project

Completed GoMC-PMTS-2024-1156
Project Description

-Installation of 3KM 3” diameter Itenge rising main. Submersible pump, control panel, solarization,2.5Km Makongo, Kyambalasi, Kilolo rising main 2Km Nzouni rising main

Budget & Expenditure
Approved
KES 5.00M
Contract
KES 4.69M
Spent
KES 4.22M
Utilisation
84.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1156
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start25 Nov 2024
  • End25 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 02 Oct 2024
Floated
Phase Two · 13 Nov 2024
Awarded
Phase Two · 22 Nov 2024
Site Handover
Phase Three · 29 Nov 2024
Not Started
Phase Two · 29 Nov 2024
Ongoing
Phase Three · 30 Nov 2024
Completed
Phase Three · 14 May 2025