Excavation Of Syengoni Earth Damdam

Completed GoMC-PMTS-2024-6757
Project Description
Excavation of the dam using county machinery
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 1.55M
Utilisation
51.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6757
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 17 Dec 2024
Approved Requisition
Phase Two · 17 Dec 2024
Floated
Phase Two · 21 Jan 2025
Awarded
Phase Two · 12 Feb 2025
Site Handover
Phase Three · 02 Mar 2024
Not Started
Phase Three · 02 Mar 2024
Ongoing
Phase Three · 12 Mar 2024
Completed
Phase Three · 24 Feb 2025