Opening Of And Ugrading Of Kwa Power, Kwa Solomon, Kasarani, Mikuyuni Secondary, Kyanzili Kavete Wayani Road

Completed GoMC-PMTS-2024-9469
Project Description

opening of and ugrading of Kwa power, Kwa Solomon, Kasarani, Mikuyuni Secondary, Kyanzili Kavete Wayani Road

-Road opening,

-8.5km grading,

-2km spot gravelling,

-Installation of culverts(900mm-1line, 600mm-4lines) 

- Cut off mitre drains for road run-off harvesting

Budget & Expenditure
Approved
KES 5.90M
Contract
KES 5.00M
Spent
KES 5.00M
Utilisation
84.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9469
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Apr 2024
  • End20 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 15 Mar 2024
Awarded
Phase Two · 18 Apr 2024
Site Handover
Phase Three · 21 May 2024
Not Started
Phase Two · 21 May 2024
Ongoing
Phase Three · 21 May 2024
Completed
Phase Three · 19 Sep 2024