Emali Township Borehole

Completed GoMC-PMTS-2024-1161
Project Description

Solarisation and equipping of Emali Township Borehole

Communal water point infranstructure

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.85M
Spent
KES 1.85M
Utilisation
92.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1161
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start06 Dec 2024
  • End06 Feb 2025
Timeline
Cabinet Paper Approved
Phase One · 01 Nov 2024
Approved Requisition
Phase Two · 11 Nov 2024
Floated
Phase Two · 15 Nov 2024
Awarded
Phase Two · 04 Dec 2024
Site Handover
Phase Three · 11 Dec 2024
Not Started
Phase Two · 11 Dec 2024
Ongoing
Phase Three · 13 Dec 2024
Completed
Phase Three · 07 May 2025