Ngiitini Borehole Solarization And Distribution

Completed GoMC-PMTS-2024-3841
Project Description

Ngiitini borehole Solarization and distribution - Solarization, elevated storage tank and distribution of the water to Kivani clusters (Ngiitini, Kyuluni and Kyangungi villages) each village served by a water kiosk 

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 3.75M
Spent
KES 3.74M
Utilisation
93.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3841
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start03 Dec 2024
  • End03 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 30 Sep 2024
Floated
Phase Two · 29 Oct 2024
Awarded
Phase Two · 27 Nov 2024
Site Handover
Phase Three · 04 Dec 2024
Not Started
Phase Two · 10 Dec 2024
Ongoing
Phase Three · 13 Dec 2024
Completed
Phase Three · 25 Mar 2025