Drilling And Equipping Muthungue Boreholeborehole

Completed GoMC-PMTS-2024-4109
Project Description

Hydro logical survey, drilling and test pumping

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 0.00
Spent
KES 3.50M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4109
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Nov 2024
  • End30 Dec 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Sep 2024
Approved Requisition
Phase Two · 18 Sep 2024
Floated
Phase Two · 15 Nov 2024
Awarded
Phase Two · 07 Nov 2024
Site Handover
Phase Three · 14 Nov 2025
Not Started
Phase Three · 14 Nov 2025
Ongoing
Phase Three · 15 Nov 2024
Completed