Hydrological Survey, Drilling And Test Pumping At Mang'elete

Completed GoMC-PMTS-2024-6063
Project Description

Hydro logical survey, drilling and test pumping

Budget & Expenditure
Approved
KES 1.80M
Contract
KES 0.00
Spent
KES 1.80M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6063
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Dec 2024
Approved Requisition
Phase Two · 12 Jan 2025
Floated
Phase Two · 18 Jan 2025
Awarded
Phase Two · 25 Jan 2025
Site Handover
Phase Three · 30 Jan 2025
Not Started
Phase Three · 30 Jan 2025
Ongoing
Phase Three · 25 Feb 2025
Completed
Phase Three · 14 May 2025