Rehabilitation Of Kwa Kalekye Borehole

Completed GoMC-PMTS-2024-1046
Project Description

Mobilization and demobilization to and from site of equipment

Installation of 3.5 km distribution pipeline

Construction of 150m3 masonry tank

Rehabilitation of 2No watering points with 5m3water tanks

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 3.70M
Spent
KES 3.70M
Utilisation
92.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1046
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start09 Jan 2024
  • End09 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 29 Oct 2024
Approved Requisition
Phase Two · 07 Nov 2024
Floated
Phase Two · 21 Nov 2024
Awarded
Phase Two · 23 Dec 2024
Site Handover
Phase Three · 13 Dec 2024
Not Started
Phase Two · 13 Dec 2024
Ongoing
Phase Three · 07 Dec 2024
Completed
Phase Three · 30 May 2025