Maintenance of Kivandini- Yathonza road, mikwani -Kombai road &Febi-Makuli road

Completed GoMC-PMTS-2024-1210
Project Description

Installation of culverts along Kivandini- Yathonza road, 60m culvert, 35 No of gabions,80m3 catch water drain

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 0.00
Spent
KES 3.70M
Utilisation
92.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1210
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 21 Jan 2025
Awarded
Phase Two · 19 Feb 2025
Site Handover
Phase Three · 20 Feb 2025
Not Started
Phase Three · 20 Feb 2025
Ongoing
Phase Three · 20 Feb 2025
Completed