Opening And Grading Of Mutinda- Mbalu-kitheini Pri-makuli-nichodemus-kwa Matheka Road

Completed GoMC-PMTS-2024-8666
Project Description

2.8km road grading, 2.8m road opening, 48m culverts,8 No of gabbions, 300cm3 catch water

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 4.62M
Spent
KES 3.69M
Utilisation
92.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8666
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start21 Feb 2025
  • End21 Apr 2025
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 10 Dec 2024
Awarded
Phase Two · 13 Jan 2025
Site Handover
Phase Three · 21 Feb 2025
Not Started
Phase Two · 21 Feb 2025
Ongoing
Phase Three · 21 Feb 2025
Completed
Phase Three · 20 May 2025