Installation Of Highmast Floodlight At Mutyambua Market

Completed GoMC-PMTS-2024-9119
Project Description

Installation of 20M high mast floodlight with 6No. 400W LED fittings

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.89M
Spent
KES 1.89M
Utilisation
94.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9119
  • WardMbitini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start10 Feb 2025
  • End12 May 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 15 Oct 2024
Awarded
Phase Two · 05 Feb 2025
Site Handover
Phase Three · 10 Feb 2025
Not Started
Phase Three · 10 Feb 2025
Ongoing
Phase Three · 10 Feb 2025
Completed
Phase Three · 16 Jun 2025