Kituiuni Junction – Mutanda Primary

Completed GoMC-PMTS-2024-6332
Project Description

 Construction of culverts, road grading, 2.5kms road spot maruming and 5.5kms spot slabs along Kituiuni Junction – Mutanda primary road.

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.86M
Spent
KES 2.85M
Utilisation
96.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6332
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start23 Feb 2024
  • End24 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 22 Dec 2023
Awarded
Phase Two · 19 Feb 2024
Site Handover
Phase Three · 21 Feb 2024
Not Started
Phase Two · 21 Feb 2024
Ongoing
Phase Three · 23 Feb 2024
Completed
Phase Three · 28 Jun 2024