Opening And Grading Of Wito Farm-mbavini- Kaiani-sinai-ctti-nguthunu-nditiku-kwa Kaunda Road

Completed GoMC-PMTS-2024-3843
Project Description

7km road opening,7km road grading, 24m culvert, 160cm3 catch water drains

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 2.77M
Utilisation
92.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3843
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 31 Jan 2025
Awarded
Phase Two · 14 Feb 2025
Site Handover
Phase Three · 06 Mar 2025
Not Started
Phase Three · 06 Mar 2025
Ongoing
Phase Three · 13 Mar 2025
Completed
Phase Three · 10 Jun 2025