Installation of High Mast Floodlight At Yinthungu Market

Completed GoMC-PMTS-2024-2339
Project Description

Installation of 20M high mast floodlight with 6No. 400W LED fittings

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.89M
Spent
KES 1.95M
Utilisation
97.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2339
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start11 Nov 2024
  • End28 Feb 2025
Timeline
Cabinet Paper Approved
Phase One · 24 Sep 2024
Approved Requisition
Phase Two · 26 Sep 2024
Floated
Phase Two · 15 Oct 2024
Awarded
Phase Two · 08 Nov 2024
Site Handover
Phase Three · 11 Nov 2024
Not Started
Phase Two · 11 Nov 2024
Ongoing
Phase Three · 11 Nov 2024
Completed
Phase Three · 16 Jan 2025