Construction Of Key Wall At Londokwe Along Nzouni- Manza Road

Completed GoMC-PMTS-2024-9971
Project Description

construction of 40m keywall

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.90M
Spent
KES 1.90M
Utilisation
94.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9971
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start12 Nov 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 15 Oct 2024
Awarded
Phase Two · 12 Nov 2024
Site Handover
Phase Three · 04 Nov 2024
Not Started
Phase Two · 04 Nov 2024
Ongoing
Phase Three · 12 Nov 2024
Completed
Phase Three · 12 Feb 2025