Installation Of Floodlights in Kitise Kithuke markets

Completed GoMC-PMTS-2024-2753
Project Description

Fabrication of a 8.5M high flood light mast, excavation and mounting the starter bars, casting of starter bars slab and mounting of the mast, fixing 1No. 150W Integrated Solar lights in mayuu, Kwa nyaa, kithayoni, katangini, mwakini ,nzouni, winzeni, kingangi, rehabilitation - ngunguuni, yinthungu, kyase, Mwania

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 3.68M
Spent
KES 1.80M
Utilisation
60.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2753
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start20 Dec 2024
  • End04 Apr 2025
Timeline
Cabinet Paper Approved
Phase One · 25 Oct 2024
Approved Requisition
Phase Two · 30 Oct 2024
Floated
Phase Two · 14 Nov 2024
Awarded
Phase Two · 20 Dec 2024
Site Handover
Phase Three · 30 Jan 2025
Not Started
Phase Three · 30 Jan 2025
Ongoing
Phase Three · 30 Jan 2025
Completed
Phase Three · 19 Jun 2025