Gravelling, Installation Of Culverts, Gabions And Drifts Along Kathamboni Spill Way

Completed GoMC-PMTS-2024-9098
Project Description

Excavation, filling and installation of culvert

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 2.85M
Spent
KES 2.85M
Utilisation
94.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9098
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start10 Dec 2024
  • End28 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 17 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 14 Oct 2024
Awarded
Phase Two · 06 Dec 2024
Site Handover
Phase Three · 10 Dec 2024
Not Started
Phase Two · 10 Dec 2024
Ongoing
Phase Three · 15 Dec 2024
Completed
Phase Three · 17 Jan 2024