Opening,grading And Road Structures OfLondokwe- Mbuvo Nzau- Munathi- Syethe- Kwa Mbalya Road

Completed GoMC-PMTS-2024-2487
Project Description

6km road opening,6km road grading, 24m culvert 4 No of gabbions,240cm3 water catch drains along Londokwe - Mbuvo- Nzau - Kwa Mbalya road

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 2.78M
Utilisation
92.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2487
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 19 Mar 2025
Awarded
Phase Two · 07 Apr 2025
Site Handover
Phase Three · 23 Apr 2025
Not Started
Phase Three · 23 Apr 2025
Ongoing
Phase Three · 28 Apr 2025
Completed
Phase Three · 16 Jun 2025