Kaumoni - Nthangathi - Kitutu Road

Completed GoMC-PMTS-2024-8987
Project Description

Construction of 3 short drifts

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.85M
Spent
KES 2.83M
Utilisation
96.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8987
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Feb 2024
  • End24 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 31 Oct 2023
Floated
Phase Two · 23 Nov 2023
Awarded
Phase Two · 03 Jan 2024
Site Handover
Phase Three · 21 Feb 2024
Not Started
Phase Two · 21 Feb 2024
Ongoing
Phase Three · 21 Feb 2024
Completed
Phase Three · 01 Mar 2024