Kanini Kaseo- Kwa Ngumu- Mt. Carmel- Kwa Wakata Road

Completed GoMC-PMTS-2024-8478
Project Description

5.5km road opening,14km heavy grading, 0.5kms spot gravelling, Installation of  36m 600mm dia and excavation of 100cm catch water drains 100cm along Kanini kaseo-Kwa Ngumu-Mt.Carmel- Kwa wakata road

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 0.00
Spent
KES 3.70M
Utilisation
92.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8478
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 14 Jan 2025
Awarded
Phase Two · 12 Feb 2025
Site Handover
Phase Three · 20 Feb 2025
Not Started
Phase Three · 20 Feb 2025
Ongoing
Phase Three · 20 Feb 2025
Completed
Phase Three · 17 Jun 2025