Makutano-Kyaani -Kiuani - Vololo road

Completed GoMC-PMTS-2024-1777
Project Description

 3Kms road widening , 6.3Kms grading , installation of  Culverts 16m, gabions 15No, 0.9km spot gravelling, and intallation of 315cm Catch water drains along  Makutano-Kyaani -Kiuani - Vololo road

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 911.9K
Utilisation
30.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1777
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 14 Jan 2025
Awarded
Phase Two · 03 Feb 2025
Site Handover
Phase Three · 19 Feb 2025
Not Started
Phase Three · 19 Feb 2025
Ongoing
Phase Three · 20 Feb 2025
Completed