Road Improvement Programme In Nguu/masumba Through Opening Across The Ward

Completed GoMC-PMTS-2024-8064
Project Description

Road Widening - 13.4Kms, Heavy grading -13.4Kms, 585cm of Catch water drains  along masumba - Yikivumbu- Kwa Nthei - Kyeni -Ndivuni- Ndatani Road, Kwa John - Kwa Pius Muangeni Catholic - Kwa Mukula - Lalonya - Ndunguni - Muuoni river road, Kuikumini - Kwa Kaluki - Matongole - Itaava road

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 2.76M
Utilisation
91.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8064
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 19 Jan 2025
Approved Requisition
Phase Two · 21 Jan 2025
Ongoing
Phase Three · 10 Feb 2025
Completed
Phase Three · 24 Apr 2025