Mukaa Road Improvement

Completed GoMC-PMTS-2024-9217
Project Description

Construction of culverts and drainage structures

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.50M
Spent
KES 1.50M
Utilisation
99.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9217
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Nov 2023
  • End15 Dec 2023
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 22 Sep 2023
Floated
Phase Two · 29 Sep 2023
Awarded
Phase Two · 03 Nov 2023
Site Handover
Phase Three · 09 Nov 2023
Not Started
Phase Two · 09 Nov 2023
Ongoing
Phase Three · 10 Nov 2023
Completed
Phase Three · 22 Nov 2023