Rehabilitation Tuvilani-kiongwani Girls-kavuko-kwawala-rubis Petrol Station Road

Completed GoMC-PMTS-2024-7772
Project Description

Opening, grading, murraming, installation structures and drainage of Tuvilani-Kiongwani Girls-Kavuko-Kwawala-Rubis Petrol Station Road

Budget & Expenditure
Approved
KES 3.10M
Contract
KES 0.00
Spent
KES 2.86M
Utilisation
92.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7772
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 13 Feb 2025
Awarded
Phase Two · 05 Mar 2025
Site Handover
Phase Three · 11 Mar 2025
Not Started
Phase Three · 11 Mar 2025
Ongoing
Phase Three · 18 Mar 2025
Completed
Phase Three · 04 Jun 2025