Routine maintenance of MAkindu ward access roads

Completed GoMC-PMTS-2024-4857
Project Description

Hire of Shovel 51 hours,27.3km  grading along 5.6km Stockyard to Mulili, 2.6km Kwa Kimongo - simba, 3.2km Skygo - St.Matthew - Kiambani road, 1.2km Airstrip to kwa Kimuyu Church road, 7.5kmNthia - malivini - Mbiuni road,7.2km Kwa Kijana - Syusyani - Yiiani road.

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 0.00
Spent
KES 3.25M
Utilisation
92.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4857
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 11 Feb 2025
Awarded
Phase Two · 28 Feb 2025
Site Handover
Phase Three · 11 Mar 2025
Not Started
Phase Three · 11 Mar 2025
Ongoing
Phase Three · 11 Mar 2025
Completed
Phase Three · 06 May 2025