Rehabilitation Of Kasikeu – Mutweamboo – Kwa Ndiki – Ndumbini – Mombasa Road

Completed GoMC-PMTS-2024-8724
Project Description

Drift construction, box culverts reinstatement spot murraming and drainage structures along Kasikeu – Mutweamboo – Kwa Ndiki – Ndumbini – Mombasa road

Construction of 75m*6m drift

240m2 Stone pitching

Demolishing structure

Graveling on 500m

construction of 150 scour checks

Budget & Expenditure
Approved
KES 10.84M
Contract
KES 10.84M
Spent
KES 10.84M
Utilisation
100%
Budget Utilisation
Gallery (1 photos)
Project Management Committee Inspecting Mutwemboo Drift During The Joint Inspection
Project Management Committee Inspecting Mutwemboo Drift Duri
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8724
  • WardKasikeu
  • Sub-CountyKilome
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceEmergency fund
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start18 Dec 2023
  • End14 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 21 Sep 2023
Floated
Phase Two · 26 Oct 2023
Awarded
Phase Two · 14 Dec 2023
Site Handover
Phase Three · 18 Dec 2023
Not Started
Phase Two · 18 Dec 2023
Ongoing
Phase Three · 18 Dec 2023
Completed
Phase Three · 27 Mar 2024