Installation Of Road Structures Along Kwakitavu Road

Completed GoMC-PMTS-2024-3100
Project Description

Construction of 25mx5m masonry drift and 7No. Gabions along Kwakitavu road

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 945.0K
Spent
KES 9.45M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3100
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Nov 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 16 Oct 2024
Awarded
Phase Two · 25 Oct 2024
Site Handover
Phase Three · 12 Nov 2024
Not Started
Phase Two · 12 Nov 2024
Ongoing
Phase Three · 12 Nov 2024
Completed
Phase Three · 11 Nov 2024