Road improvement programme through road opening in Mbooni ward

Completed GoMC-PMTS-2024-7048
Project Description
27.5kms light grading, 25kms light bush clearance and mitre- drain excavation 150m of catch water drains
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 1.89M
Utilisation
94.4%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
Spot improvement of Matondoni -Uvaa- Kituku- Red sea KES 30.00M KES 0.00 Ongoing
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7048
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 24 Sep 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 20 Feb 2025
Awarded
Phase Two · 24 Mar 2025
Site Handover
Phase Three · 24 Apr 2025
Not Started
Phase Three · 24 Apr 2025
Ongoing
Phase Three · 01 May 2025
Completed
Phase Three · 30 Jan 2025