Kangesu -– Ithambaume – Kwa Nzinga – Gff – Mutokwe Ecde Road

Completed GoMC-PMTS-2024-5379
Project Description

4Kms heavy Bush clearing ,  8.5Kms heavy grading , 1km gravelling , installation of 24m  (600mm dia.) Culverts,construction of  15No. Gabions, 40m RC keywall, 30mx6m wide ridding surface, and 550m3 of Catch water drains along Kangesu -– Ithambaumme – Kwa Nzinga – GFF – Mutokwe ECDE road

Budget & Expenditure
Approved
KES 5.00M
Contract
KES 0.00
Spent
KES 4.62M
Utilisation
92.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5379
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 24 Jan 2025
Awarded
Phase Two · 06 Feb 2025
Site Handover
Phase Three · 24 Feb 2025
Not Started
Phase Three · 24 Feb 2025
Ongoing
Phase Three · 24 Feb 2025
Completed
Phase Three · 20 Mar 2025