Road Grading And Culvert Installation Along Kwa Nzelu-ndandini-kyevutula-munyeetani

Completed GoMC-PMTS-2024-3540
Project Description

7km bush clearing, 7kms heavy grading, Installation of culvets 4om and 340.2m3 cut-off mitre drains

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 1.85M
Utilisation
92.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3540
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 05 Dec 2024
Awarded
Phase Two · 05 Feb 2025
Site Handover
Phase Three · 10 Feb 2025
Not Started
Phase Three · 10 Feb 2025
Ongoing
Phase Three · 10 Feb 2025
Completed
Phase Three · 28 Mar 2025