Survey, Road Opening And Widening And Murraming Of Kwa Titus-aic Mbiuni-kwa Iwaikanga Road

Completed GoMC-PMTS-2024-3002
Project Description

7km mechanical road opening, 7km heavy grading, installation of 24m culverts and 863.46m cut off mitre drains along Kwa Titus-Aic Mbiuni-kwa IwaIkanga Road

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 3.70M
Spent
KES 3.50M
Utilisation
87.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3002
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Mar 2025
  • End09 Jun 2025
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 31 Jan 2025
Awarded
Phase Two · 04 Mar 2025
Site Handover
Phase Three · 11 Mar 2025
Not Started
Phase Three · 11 Mar 2025
Ongoing
Phase Three · 12 Mar 2025
Completed
Phase Three · 29 May 2025