Installation Of Floodlights At Mbiiani ,nthungoni,katungoli, Kwa Kulomba And Kavutini Markets

Completed GoMC-PMTS-2024-6737
Project Description

Installation of 15M grid connected 4-arm floodlights at Mbiiani ,Nthungoni,Katungoli, Kwa Kulomba and Kavutini Markets

Rehabilitation of existing market lights at Kwa Ndunda, Utuneni and Namba Nyanya markets

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 2.80M
Utilisation
93.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6737
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 20 Nov 2024
Approved Requisition
Phase Two · 21 Nov 2024
Floated
Phase Two · 08 Jan 2025
Awarded
Phase Two · 28 Jan 2025
Site Handover
Phase Three · 31 Jan 2025
Not Started
Phase Three · 31 Jan 2025
Ongoing
Phase Three · 31 Jan 2025
Completed
Phase Three · 27 Jun 2025